View from site 3 – University of Bath School of Management

Following on from the successful completion of the enabling works contract Bouygues UK have been appointed as Main contractor. The site set up for the main works is well underway with two tower cranes erected and the concrete frame contractor – Blanchard Wells on site. Mann Williams have been Novated to Bouygues UK for full Civil and Structural construction stage design and detailing. A Value Engineering phase has been undertaken with the team and a number of building and structural alterations have been integrated into the completed Enabling works Contract. The first main pour of the 18m clear span lecture theatre transfer slab is due in early December.